Question: 1 / 175

What is meant by "Late Finish" in project management?

The most delayed completion time for any project

The latest an activity can finish without delaying the overall project

"Late Finish" in project management specifically refers to the latest possible point in time that an activity can be completed without causing a delay to the overall project's completion date. This concept is part of the critical path method, which helps to determine the scheduling and timing of project activities.

When planning a project, it is essential to establish not only when tasks must start and finish but also to understand the flexibility available in the schedule. The Late Finish is critical for identifying the float or slack available for each activity. By knowing the Late Finish, project managers can assess risks, allocate resources effectively, and prioritize tasks that might be on the critical path.

Understanding the Late Finish allows project managers to ensure that any adjustments made to the project schedule do not adversely affect the overall timeline, maintaining project control and focus on deadlines. This concept is foundational for effective project scheduling and resource management.

The total project end date

The time after which project reviews occur